Project Details
Work Type Repaving
Phase Construction
Limits From the Hillsborough County line to south of SR 39 (Paul Buchman Hwy)
Project Start October 2, 2023
Length 3.8 miles
City
County
Road
Construction Cost $6.75 million
Estimated Completion Summer 2024
Contractor Burgess Civil, LLC
About

This project will repave US 301 in Pasco County from the Hillsborough County line to just south of SR 39 (Paul Buchman Highway).

Other project work includes curb and gutter, sidewalk, signing, pavement markings, lighting, pedestrian and vehicle signal upgrades, and drainage improvements.

Street lighting will be installed at the US 301 / Chancey Road intersection and at the merge of US 301 and SR 39 (Paul Buchman Hwy).

Construction began October 2, 2023.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • US 301 (Gall Blvd.) from the Hillsborough County line to SR 39 (Paul Buchman Highway)
    Periodic flagging and delays for traffic stops: Sunday, April 21 through Thursday, April 25 nights from 7 p.m. to 6 a.m.