EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type Repaving
Phase Construction
Limits From west of Little Road to Marathon Road
Project Start February 16, 2024
Length 3.4 miles
City
County
Road
Construction Cost $12.7 million
Estimated Completion Spring 2025
Contractor Ajax Paving Industries of Florida LLC
About

This project will repave SR 54 between Little Road and Marathon Road.  The existing sidewalk on the north side of SR 54 between Starkey Boulevard and Success Drive and between Success Dr. and Marathon Road will be widened to eight feet.

 Pedestrian features will be added at the Hospital Boulevard intersection and a new mid block pedestrian crossing will be added east of Starkey Boulevard across SR 54.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • SR 54 from west of Little Road to Marathon Road
    Lane closures: Monday, April 22 through Friday, April 26 from 7 a.m. to 4 p.m.