Project Details
Work Type Repaving
Phase Completed
Limits From west of Little Road to Marathon Road
Length 3.4 miles
City
County
Road
About

As of June 30, 2025, all construction activities associated with this project have been completed.  

This project repaved SR 54 between Little Road and Marathon Road.

The existing sidewalk on the north side of SR 54 between Starkey Boulevard and Success Drive and between Success Dr. and Marathon Road was widened to eight feet. Pedestrian features were added at the Hospital Boulevard intersection and a new mid block pedestrian crossing across SR 54 was built east of Starkey Boulevard.

_________________________________________

Mid-block pedestrian signals are now operational on SR 54 east of Starkey Boulevard

April 24, 2025 -- New mid-block pedestrian signals have been activated on SR 54 just east of Starkey Boulevard. The new signals and crosswalk allow pedestrians to cross the busy highway more safely. Drivers are asked to be alert to the new crosswalk and prepared to stop for pedestrians.

How the signals work
For Pedestrians: They will push a button that will activate the traffic signal. After the traffic signal turns red, pedestrians will get a walk signal and a countdown timer. Once the walk sign is displayed on the pedestrian signal and they observe vehicles stopping, pedestrians may cross the highway.

For Drivers: The signals will operate like regular intersections (but at midblock where there is no crossroad). When a pedestrian pushes a button, the signal will turn yellow and then red. The pedestrian will be given time to cross, then the signal will go back to green for drivers. Drivers should always make sure no pedestrians are in the crosswalk before advancing.

Click for a photo of the signals

View Factsheet
Contact Information
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Images
New traffic signals for mid-block crossing, east of Starkey Boulevard (4.28.2025 photo)
New traffic signals for mid-block crossing, east of Starkey Boulevard (4.28.2025 photo)
New mid-block crosswalk across SR 54 east of Starkey Road (4.28.2025 photo)
New pedestrian signals for mid-block crossing, east of Starkey Boulevard (4.28.2025 photo)
Pedestrian push button for signal activation at mid-block crossing (4.28.2025 photo)
New mid-block traffic signals are now operational at a pedestrian crossing east of Starkey Boulevard
Looking west at new pavement on SR 54 at the Corp[orate Center Drive / Success Drive intersection (4.28.2025 photo)
The right lane is closed on westbound SR 54 for construction operations (3-3-2025 photo)
The right lane is closed on westbound SR 54 for construction operations (3-3-2025 photo)
New traffic signals for midblock pedestrian crossings are coming to an area east of Starkey Boulevard (3-3-2025 photo)
"UNEVEN LANES" signs alert drivers that paving is not yet completed on SR 54 (3-3-2025 photo)
Paving is underway on the project and replacement signals will soon be activated at Starkey Boulevard (3-3-2025 photo)
Work in the median of SR 54 at Hospital Boulevard (3-3-2025 photo)
Work in the median of SR 54 at Hospital Boulevard (3-3-2025 photo)
Looking west on SR 54 at new pavement and pedestrian improvements construction at Little Road (3-3-2025 photo)
Installing storm water drainage pipe
New foundation for a midblock traffic signal pole on SR 54 east of Starkey Boulevard
Workers place concrete along westbound SR 54 to replace a broken sidewalk section west of Country Place Boulevard.
Freshly placed concrete sidewalk