EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type Repaving
Phase Construction
Limits from US 19 to west of Virginia City Dr.
Project Start February 5, 2024
Length 1.7 miles
City
County
Road
Construction Cost $5.4 million
Estimated Completion Fall 2024
Contractor Ajax Paving Industries of Florida LLC
About

This project will repave SR 54 between US 19 and Virginia City Drive in western Pasco County. 

In addition to repaving the road, medians along the corridor are being evaluated to determine if modifications are necessary to enhance safety along the roadway.

Construction began February 5, 2024. 

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
roadwork@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • SR 54 from US 19 to west of Virginia City Drive
    Day lane closures: Monday, April 22 through Friday, April 26 from 7 a.m. to 4 p.m.
    Night lane closures: Sunday, April 21 through Thursday, April 25 nights from 8 p.m. to 7 a.m.