Alt US 19 (5th Avenue N) Repaving from 6th Street N to 58th Street N 448036-1-52-01
Project Details
Work Type | Repaving |
---|---|
Phase | Completed |
Limits | From west of 6th Street to Tyrone Boulevard |
Length | 4.5 miles |
City | |
County | |
Road |
About
As of July 22, 2025, all construction activities associated with this project have been completed.
This project repaved Alt. US 19 (5th Avenue North) from west of 6th Street North to 58th Street North in St. Petersburg.
Other improvements included sidewalk enhancements, median modifications, and the addition of bicycle lanes from 6th Street North to 20th Street North.
Construction is expected to be complete in summer 2025.