Project Details
Work Type Repaving
Phase Construction
Limits From 5th Avenue N to East of Park Street N
Project Start August 17, 2025
Length 3.4 miles
City
County
Road
Construction Cost $11.3 million
Contractor Gosalia Concrete Constructors, Inc.
About

Tyrone Blvd On-Street Parking to be Unavailable

Beginning Thursday, February 5th, on-street parking will be unavailable along the frontage roads of Alt. US 19 (Tyrone Boulevard) between 13th Avenue N and 38th Avenue N.

Once parking areas are marked with cones and tape, remaining vehicles must be moved within 72 hours; failure to do so may result in impoundment at the owner’s expense. On-street parking may resume once barricades have been removed.

During these paving activities, Alt US 19 (Tyrone Boulevard) will remain open to motorists and pedestrians.

For more information on this project, please visit FDOTtampabay.com

********************************************************

This project includes rigid pavement rehabilitation for concrete pavement slabs of the existing roadway on Alt US 19 (Tyrone Boulevard) from 5th Avenue N to Park Street N in St. Petersburg. The project also includes sidewalk improvements, and mid-block pedestrian crosswalks.

Construction is anticipated to complete in Summer 2026.

Please click on the following links, for information on how to use the Pedestrian Hybrid Beacon.

TIP CARD and Information Video 

View Factsheet
Contact Information
Project Information
Maddie Griffin
727-575-8334
Maddie.Griffin@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • ALT US (Tyrone Boulevard) from 5th Ave N to Park Street
    Night lane closures: Tuesday, February 10 through Thursday, February 12 nights from 8 p.m. to 6 a.m.
    Day lane closures: Monday, February 9 from 7 a.m. to 5 p.m.

Project Images
Constructing ditch pavement (January 2026 photo)
Concrete curb restoration at Winchester Road N (January 2026 photo)
Ditch pavement concrete placement (January 2026 photo)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (November 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (November 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (November 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (November 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (October 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (October 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (October 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (October 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (October 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (September 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (September 2025)
Alt US 19 (Tyrone Boulevard) Pavement Rehabilitation from 5th Avenue to Park Street (September 2025)