Project Details
Work Type Resurfacing
Phase Construction
Limits from west of Virginia City Drive to Old Mill Pond Drive
Project Start May 7, 2025
Length 1.47 miles
City
County
Road
Construction Cost $5.4 million
Estimated Completion Early 2026
Contractor Preferred Materials Inc.
About

This project will mill and repave SR 54 from west of Virginia City Drive to Old Mill Pond Drive in the New Port Richey area of Pasco County.

The traffic signal at Rowan Road will be upgraded as part of this project. In addition, the median opening east of Rowan Road will be closed. Minor drainage and signing/pavement marking work will also take place.

The alignment of the road will not be altered from the existing conditions and all improvements will be made within the existing rights-of-way.

Day and night lane closures will be used as needed to perform the various work activities.

Construction began May 7, 2025.

View Factsheet
Contact Information
Project Information
John McShaffrey
(813) 975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kris Carson
(813) 975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • SR 54 from west of Virginia City Drive to Old Mill Pond Drive
    Lane closures: Monday, February 9 through Friday, February 13 from 7 a.m. to 5 p.m.

Project Files
Project Images
Placing thermoplastic paint on a SR 54 crosswalk at Seven Springs Boulevard (2-9-2026 photo)
Looking east over SR 54, just west of Highwater Drive (1-30-2026 photo)
Looking west over SR 54 at the Rowan Road intersection (1-30-2026 photo)
Installing traffic monitoring loops in the pavement (12-15-2025 photo)
Placing concrete for a pedestrian signal base and sidewalk (10-14-2025 photo)