Work Type New Road Construction
Phase Design
Limits From south of County Line Road to SR 56
Length 3.9 miles
City
County
Road

About

This project will construct a 3-lane southbound Collector-Distributor (CD) road system from the SR 56 southbound on-ramp to the I-75 / I-275 apex to complement the northbound CD road system in Wesley Chapel.

This includes:

  • A  new 2-lane southbound on-ramp from the CD roadway to southbound I-75, which will require widening the bridge over Cypress Creek.
  • A new bridge over Cypress Creek for the southbound CD roadway
  • A new fork of I-75 / I-275 southbound
  • A new bridge for southbound I-275 over the CD road ramp to southbound I-75
  • New concrete barrier wall separation between the southbound I-75 mainline lanes and the proposed southbound CD roadway.
  • A proposed ramp from the southbound CD roadway to southbound I-75.

The project is currently in the design phase and has been combined with FPN 430573-3.

Construction is not currently funded.

View Factsheet The link target will open in a new tab.