SR 60 (Kennedy Blvd) Repaving from Hoover Blvd to Church Ave 447975-1-52-01
Project Details
Work Type | Resurfacing |
---|---|
Phase | Completed |
Limits | From west of Hoover Blvd to Church Ave |
Length | 1.33 miles |
City | |
County | |
Road |
About
All construction activities associated with this project were completed on Thursday, December 19, 2024.
This project repaved SR 60 (Kennedy Boulevard) from west of Hoover Boulevard to Church Avenue in Tampa.
Additional improvements included upgrading the crosswalk at Hoover Boulevard.
Construction activities took place during daytime and nighttime hours.
Construction activities were estimated to finish in early 2025.
View Factsheet
Contact Information
Media Contact |
---|
Kris Carson
813-975-6202
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.