Project Details

Work Type
Resurfacing
Phase
Construction
Limits
SR 39 from north of Central Avenue to US 301/Gall Boulevard
Project Start
December 1, 2025
Length
2.769 Miles
City
County
Road
Construction Cost
$5.2 million
Estimated Completion
Fall 2026
Contractor
Pigott Asphalt and Sitework LLC

About

Improvement to this roadway segment will include milling and resurfacing, minor widening and drainage upgrades, sidewalk repairs/minor reconstruction, curb and gutter repairs/minor reconstruction, signing and pavement markings, traffic signal head replacements/enhancements at Chancey Road, and performing general safety upgrades along SR 39 in Pasco County.

Construction began in December 2025.

View Factsheet The link target will open in a new tab.

Contact Information

Closures

  • SR 39 from north of Central Avenue to US 301 (Gall Blvd.)
    Lane closures/ flagging operations: Sunday, September 27 through Thursday, October 1 nights from 7 p.m. to 7 a.m.