Project Details
Work Type Resurfacing
Phase Construction
Limits SR 39 from north of Central Avenue to US 301/Gall Boulevard
Project Start December 1, 2025
Length 2.769 Miles
City
County
Road
Construction Cost $5.2 million
Estimated Completion Fall 2026
Contractor Pigott Asphalt and Sitework LLC
About

Improvement to this roadway segment will include milling and resurfacing, minor widening and drainage upgrades, sidewalk repairs/minor reconstruction, curb and gutter repairs/minor reconstruction, signing and pavement markings, traffic signal head replacements/enhancements at Chancey Road, and performing general safety upgrades along SR 39 in Pasco County.

Construction began in December 2025.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • There are no closures at this time.
Project Images
Reminder - speeding fines are doubled when workers are present in construction zones (12-9-2025 photo)
Early in the construction project on SR 39 approaching Chancey Road (12-9-2025 photo)
Temporary barrier wall installed on the east side of SR 39 for construction work (12-9-2025 photo)
Looking south at traffic shifted on SR 39 (12-9-2025 photo)