Project Details
Work Type Resurfacing
Phase Construction
Limits SR 54 from east of Gunn Hwy to east of Crossings Blvd and SR 54A
Project Start June 23, 2025
Length 3.87 Miles
City
County
Road
Construction Cost $6.3 million
Estimated Completion early 2026
Contractor Hubbard Construction Company
About

This project will mill and repave SR 54 from east of Gunn Highway to east of Crossings Boulevard (Odessa area of Pasco County) to preserve and extend the life of the pavement. It will also include safety modifications and will improve ADA facilities along SR 54.

SR 54A (Black Lake Road) will also be repaved as part of this project.

Minor drainage and signing/pavement marking work will also take place. All improvements will be made within the existing rights-of-way.

Construction began June 23, 2025.

View Factsheet
Contact Information
Project Information
John McShaffrey
813-975-6930
john.mcshaffrey@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • SR 54 from east of Gunn Highway to east of Crossings Boulevard 
    Lane closures: Sunday, September 21 through Thursday, September 25 nights from 8 p.m. to 6 a.m.  

    SR 54 west of Lake Polo Drive 
    Around-the clock lane left turn-lane closures: Sunday September 21 through Saturday September 27