US 19 New Interchanges and Roadway Improvements from SR 580 to the north of CR 95 256774-3-52-01
Project Details
Work Type | New Interchanges |
---|---|
Phase | Construction |
Limits | From SR 580 to the north of CR 95 |
Project Start | Spring 2023 |
City | |
County | |
Road | |
Construction Cost | $242.7 million |
Estimated Completion | 2029 |
Contractor | Johnson Bros. Corporation, A Southland Company |
About
The interchange and roadway improvement project is modifying the existing six-lane divided highway to a six-lane controlled access roadway with one-way frontage roads in both directions parallel to US 19 from SR 580 (Main Street) to the north of CR 95/CR 39 in Pinellas County.
In addition, new interchanges will be added just north of Boy Scout Road and at SR 586 (Curlew Road) to improve traffic flow along this corridor.
A pedestrian underpass will be added between Evans Road and Republic Drive and a pedestrian bridge over US 19 is being constructed at Northside Drive.
Construction is estimated to finish in 2029.
Click to view the virtual presentation. - Construction open house on May 16, 2023
FDOT project numbers 256774-2 and 256774-3 have been combined into a single construction contract. All updates and alerts will be posted on this page.
*Construction cost includes original construction contract amount plus approved contract changes. It does not include inspection oversite.
Please click on the following link to learn more about staying safe in work zones: Work Zone Safety It's Everyone's Job
Contact Information
Project Information |
---|
Bryce Johns
727-575-8334
Bryce.Johns@dot.state.fl.us
|
Media Contact |
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
-
US 19 from SR 580 (Main Street) to SR 586 (Curlew Road)
Lane closures: Sunday, September 21 through Thursday, September 25 nights from 8 p.m. to 6 a.m.