Project Details
Work Type New Highway lighting
Phase Construction
Project Start Early 2021
City
County
Road
Construction Cost $698,558
Estimated Completion Fall 2021
Contractor PowerCore, Inc.
About

This project will install street lighting at various intersections in Pinellas County. This will increase the visibility of pedestrians within the crosswalks at these signalized intersections.

  • 5th Ave N. at 19th St. N, 20th St. N. Tyrone Blvd,
  • Tyrone Blvd at 9th Ave. N, 22nd Ave N., 66th St. N, 68th St. N, 80th St. N./ 38th Ave. N.
  • Bay Pines Blvd at 100th Way
  • 4th Ave. N at 4th St. N
  • East Bay Dr. at  NB US 19 Frontage Rd and  SB US 19 Frontage Rd. 
  • Roosevelt Blvd. at Dodge St., 62nd St. N, 58th St. N, Lake Carillon Dr./28th St. N, 16th Ct. N, /16th St. N., Dr. MLK Jr. St/ 9th St. N, Gandy Blvd
  • 4th St. N at Gandy Blvd. S Frontage, Gandy Blvd N. Frontage, 3rd Ave. N., 2nd Ave. N, 1st Ave. N, 1st Ave S, 2nd Ave. S, 4th Ave. S.
  • Ulmerton Road at Wilcox Rd.
  • US 19 SB Frontage Rd at Whitney Rd, 66th St. N, 126th Ave. N,
  • US 19 NB Frontage Rd at Whitney Rd, and 126th Ave. N.
  • 66th St. N at 118th Ave. N

Construction is anticipated to begin in early 2021 and be complete in the fall of 2021.

 

 

View Factsheet
Contact Information
Construction Manager
Sarah Gansz
727-575-8300
Sarah.Gansz@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.carson@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.