Bridge Maintenance Pinellas County Multiple locations 443833-1-52-01
This project has been completed. The information on this webpage is archived for reference and research purposes.
Project Details
| Work Type | Bridge Maintenance |
|---|---|
| Phase | Completed |
| Limits | SR 580, US 19, SR 580, SR 688, SR 679 |
| City | |
| County | |
| Road |
About
FINAL ACCEPTED ON JANUARY 5, 2021
This project will replace or repair the bearing pads and plates on bridges in Pinellas County at the following locations;
- SR 60 at the Clearwater Harbor
- US 19 over 49th St.
- US 19 Over Drew St.
- US 19 over SR 688 (Ulmerton Road)
- SR 580 over Safety Harbor Bay
- SR 679 at Bunces Pass
The project is anticipated to begin during the fall of 2020 and finish in the spring of 2021.